تحليل مخاطر المشروعات على وفق نظام ادارة المشاريع الاحترافية : دراسة حالة في شركة المنصور العامة للمقاولات الانشائية == Risk Analysis of Projects Accordance With The Professional Project Management System : Acase - Study Mansour Construction Contracting Company
Author name:
سلوى صالح علي
Supervisor name:
نغم حسين نعمة
General topic:
Administration and Economics
Specific topic:
Performance Evaluation
Degree:
Master
University:
University of Baghdad - Faculty Of Administration And Economics - Department Of Business Administration
Language:
Arabic
University location:
Baghdad
First pages:
07T3742 - p.pdf
Abstract:
تتميز مشاريع التشييد بخصوصيتها وكثرة العوامل المؤثرة فيها البحث الى ادارة مخاطر المشروعات وفق العمليات المتعلقة بتخطيط المخاطر والتعرف عليها وتحليلها ومواجهتها والسيطرة عليها وتتمثل اهداف ادارة المخاطر في المشروع في زيادة احتمالية وتاثير الاحداث الايجابية | Characterized by construction projects conservatively and the many factors affecting it, making it vulnerable to the uncertainties and risks that may affect the goals Almttmlh (cost, time, scope, quality). The identified research problem that working in the field of project management companies lacking to provide the necessary requirements for risk management and the application of project management professional methodology of construction projects and of each of (the availability of indicators and criteria for risk analysis and methods and methods of analysis form, and to identify whether there is a descriptive indicators or the amount indicate a risk in the project and whether the project is available or quantitative indicators and descriptive to measure and identify those risks and how responsive project management (sample) to those risks.And research aimed at ERM in accordance with the processes related to the planning of risk and identification and analysis and response and control by increasing the probability and impact of positive events and minimize the likelihood and impact of negative events in the project processes of risk management in accordance with the project management professional the PMP system (Project Management Professional) include identifying priority the specific risks and implications of the goals of the project in the case of those risks occurring and to provide appropriate risk planned responses depending on the importance of risk so that they are economically and realistic cost and in the context of the project and agreed upon by all participants in the project parties and submit periodic reports to the project manager on the effectiveness of the plan, or any effects unexpected or processing required to respond to the risk of a Mnasp.az been applied to research on a sample of five implementing projects by the General Mansour Construction Contracting company, a (Faculty of law, Faculty of floating Islamist, genetic Engineering Institute, Baghdad governorate building, the project hit the residential complex) and points Miscellaneous (University of Baghdad, the provincial council, the public Authority for Housing) has been using the style of a personal interview with the heads of departments in the Al - Mansour and project managers research sample and the Working Group with them as well as the use of the checklist to identify the degree and level of risks in the projects implemented by the company's projects and analysis of descriptive and quantitative where the use of tools (probability and impact of risk analysis scheme Ai_kaoa Sbb - effect, analysis of probability and impact, risk matrix (probability and impact), decision tree analysis) and research found to the high amount of risk in the projects implemented by the company and the reason for this is the lack of hand specialized project Management risks and a lack of risk management plans as a result of lack of awareness by management and personnel effects and the importance of planning and risk analysis on the success of the projects, in terms of availability of qualified human resources required for their application, techniques and thereby to reduce a large proportion of the risks and to provide the appropriate response for the remaining risk